Plan for dams put on faster track
July 31, 2008
By Edward Husar
The Federal Energy Regulatory Commission last week
completed its review of
The authorization "is an important step"
for the project, said Mike Klingner, president of Klingner and Associates of Quincy, one of the engineering
firms designing plans to install hydroelectric plants at Lock and Dam 20 in
Klingner said being able to follow a traditional licensing process
means
"You don't have to go through so many extra
hoops," Klingner said. "It's a little more
streamlined, a little faster. And we got the approval faster than we were
anticipating."
FERC is now requiring the city to schedule site
visits to all three dams -- along with a joint meeting -- for various federal,
state and local governmental entities with a stake in the projects. Klingner said the site visits have been tentatively
scheduled for Sept. 9, and the joint meeting is slated for Sept. 10.
"We will be issuing a public notice of the
meetings within the next 30 days," Klingner
said.
"I think it's wonderful that we're getting
the green light from FERC to move forward with our project," Spring said. "We're just so happy that we're staying
right on course, right on schedule, as we continue to be proactive in trying to
find an alternative source of energy for this region."
The upcoming site visits will let representatives
of governmental agencies see firsthand where the hydroelectric facilities would
be located. The agencies could then request studies to address any concerns
they might have, including environmental issues.
Klingner said the U.S. Army Corps of Engineers, the Illinois
Department of Natural Resources, the Missouri Department of Natural Resources
and the Environmental Protection Agencies from both states will be among the
agencies invited.
Plans call for installing 40 500-kilowatt
generators at
Combined, the three plants would be able to
produce up to 50 megawatts at maximum capacity. But because hydro plants don't
always operate at maximum because of fluctuations in water levels, the three
sites are expected to produce an average power output of 19 megawatts.
That's equivalent to the amount of electricity
consumed on a regular basis by all 12,000 residential households in
Klingner said
"Head" refers to the drop in elevation
from the upper pool above a dam to the lower pool below the dam. The elevation
drop is much more pronounced at the Quincy and Saverton
dams, and not as pronounced at
Last week, Claude O'Neil, president of Novatech-Lowatt Turbines Inc. of
Klingner said "it looks very positive" that the city
should be able to use the new turbines, which have the added benefit of being
less harmful to fish than traditional hydropower turbines.
If everything goes as planned, the hydropower facilities
could be operational by late 2015 or early 2016 at a cost of about $200
million.
Spring said the city will be seeking federal and
state appropriations to help pay for engineering studies over the next four
years leading up to the issuance of licenses, but not for the construction or
operation of the hydropower plants. The city would handle those costs on its
own, likely with revenue bonds financed by the sale of electricity.