Capital projects reach crossroads
January 5, 2009
By Steve Eighinger
Four major Quincy Park
District capital projects should -- or at least could -- reach completion or
move to their next phases in 2009.
The four projects, which
currently total $7.3 million and will easily reach $10 million or more at some
point, involve work at Bob Mays, Washington and Boots Bush parks, plus the
Cedar Creek Linear Parkway.
The first of three
development phases at
Parks said district crews
will be finishing up the "Alle of Trees"
soft surface trail and tying up "a few loose ends" that will complete
the $500,000 first phase of development at the 53-acre site. Among the other
amenities in that first phase are a picnic shelter and restroom, a playground,
and parking lot.
There is no timetable for
the completion -- or even the start -- of the remaining two phases, which will
cost $1 million at today's prices. Those phases are scheduled to include a
4.5-acre lake, a second shelter/restroom, tennis and basketball courts, and a
south loop road.
"There is no funding
available at this time," said Parks, who outlined how the district is in
constant pursuit of state and federal grants for such items.
The park was dedicated
last summer and served as the new headquarters area of the Breakfast Optimist
Club-sponsored Soap Box Derby.
The Cedar Creek project
will eventually stretch from
The first phase of Cedar
Creek will carry a $1.3 million price tag, with the second phase between Fifth
and 12th streets currently sitting at $2.4 million. There is no schedule in
place for the start of construction on the second phase. The district is
awaiting word on federal funding.
"The public works
stimulus package (president by President-elect Barack Obama) could aid
this," said Parks, who hopes to know if the district will receive any of
the stimulus funds by the time the first phase is completed.
The final 18 blocks of
the Cedar Creek project will likely cost at least double what the first two
phases will by the time it is completed. Neither the acquisition of all needed
property or planning costs have yet been completed for
any part of the project beyond the first two phases.
The first phase of
redeveloping
If funds materialize,
work could begin when weather permits in the spring and be completed by fall of
2009. First-phase redevelopment will include the removal of out-of-date tennis
courts west of the Flinn Stadium parking lot and
building a walkway near the area where two existing soccer fields will undergo
major redevelopment to improve the playing surfaces.
A $640,000 phase two development at Boots Bush will eventually provide for the
addition of two more soccer fields will eliminate the baseball diamond at the
park. Junior baseball programs that have use the field in the past will be
moved to
The $640,000 second phase
was scaled back earlier in the year to make the cost more workable. Half that
cost will have to be funded locally, Parks said, which means the local soccer
community will need to raise $320,000.
A $1.1 million
redevelopment of
Scheduled for early 2009
are such major items as the $200,000 replacement of the fountain in the middle
of the downtown park, plus a $100,000 upgrade of the site's electrical system
and a $100,000 upgrade of the park's irrigation system.
Parks said electrical
upgrade is especially significant because it will make the park more energy
efficient and provide an improved backdrop for special events at the site.